Project Overview
The Common Central Secretariat (CCS) 8&9 Site Office, located opposite the Air Headquarters on Kartavya Path, New Delhi, is a fast-track turnkey interior project executed for Ahluwalia. Spread across 8,800 sq. ft., the project required meticulous planning, seamless coordination, and rapid execution to create a modern, functional workspace for one of India’s landmark government infrastructure developments.
Unlike conventional furniture installations, this assignment demanded complete interior execution within an aggressive 20-day timeline, while coordinating multiple vendors and accommodating continuous site modifications. The successful completion of this project marked a significant milestone for Rockworth as it showcased the company’s ability to deliver comprehensive workplace solutions beyond furniture.
Core Team
- Sales Lead: Akash Gupta
- Project Lead: Harshit Bansal
Key Stakeholders
The project was delivered in collaboration with industry-leading partners to ensure seamless execution:
- Architect & Designer: Taru Rawat & Bhawna Mangat
- PMC (Project Management Consultant): Ahluwalia Contracts (India) Ltd.
This strong stakeholder alignment enabled efficient decision-making and smooth project progression.
The Challenge
Executing a complete turnkey interior project within 20 days required overcoming several challenges:
- Coordinating with 10+ solution partners across civil, electrical, interior, and furniture works.
- Managing work dependencies while multiple activities progressed simultaneously.
- Adapting to continuous client-driven design changes during execution.
- Ensuring timely material availability and efficient use of limited site space.

Rockworth’s Approach
To meet the aggressive timeline, Rockworth adopted a structured execution strategy:
- Parallel Execution: Multiple workstreams progressed simultaneously to reduce project duration.
- Zone-Based Planning: Dedicated work zones enabled vendors to work efficiently without disruption.
- Real-Time Monitoring: Daily progress tracking helped resolve issues quickly and keep the project on schedule.
- Agile Execution: On-site design revisions were incorporated without significantly affecting the delivery timeline.

The Outcome
The project was completed on schedule, delivering a modern and functional workspace with improved space utilization and a professional aesthetic. Careful planning and coordinated execution ensured smooth project delivery while maintaining quality throughout.
Project Deliverables
As part of the turnkey execution, Rockworth, in collaboration with Wesource, delivered and installed a comprehensive range of interior and workplace solutions, transforming the site office into a fully functional and efficient workspace. The scope included civil works such as flooring, acoustic ceilings, interior painting, bamboo work, aluminium door frames and windows, uPVC windows, HVAC (Heating, Ventilation, and Air Conditioning), plumbing, and wall tiling. In addition, Rockworth and Wesource supplied and installed complete workplace furniture, including workstations, ergonomic chairs, cabin tables, a conference table, sofas, corner and center tables, reception tables, and several other workplace elements. Every aspect of the project was meticulously planned, coordinated, and executed within the demanding timeline, resulting in a modern, functional, and aesthetically refined workspace.

What Made This Project Unique?
- Complete turnkey interior project delivered in just 20 days.
- Seamless coordination of 10+ specialized partners.
- One of Rockworth’s key turnkey interior executions beyond its core furniture expertise.
- Parallel execution enabled faster delivery without compromising quality.
- Successfully accommodated continuous client changes during execution.
- End-to-end management from planning and procurement to final handover.

Quality Standards
The completed Common Central Secretariat (CCS) 8 & 9 Site Office delivers a modern, efficient, and future-ready workplace that supports seamless government operations. Designed to maximize functionality, optimize space utilization, and enhance user comfort, the workspace balances operational efficiency with a professional aesthetic. This commitment to quality is reinforced by Rockworth’s globally certified furniture solutions, including BIFMA, AIOTA, ZED Gold, and Indoor Air Quality GOLD Certification, together with ISO-certified management systems for quality, environmental responsibility, occupational health & safety, and energy management.

Conclusion
The Common Central Secretariat (CCS) 8 & 9 Site office showcases Rockworth’s expertise in delivering fast-track turnkey interior projects for high-profile government infrastructure developments. Spanning 8,800 sq. ft., the project was successfully completed in just 20 days through strategic planning, parallel execution, real-time progress monitoring, and seamless coordination of 10+ specialized partners. Despite continuous client-driven changes and a demanding execution schedule, Rockworth delivered a modern, functional, and aesthetically refined workspace while maintaining the highest standards of quality, efficiency, and client satisfaction.